2004January 2004, and I decided the daggerboard
had got to go. It was still not very smooth, despite endless fairing,
but worse is that it didn't fit well into the trunk. I built a daggerboard blank from Airlite
and shipped it to Phil's Foils for shaping. Phil has a 3-axis
milling machine and is able to make daggerboard and rudders for just
about any boat. He will finish to any degree. I was getting close to completing the rudder,
as
well as all associated parts like case, sleeve, and brackets. I also
found out that I would be moving to Columbus, where my wife would be a
professor at Ohio State. I decided
to build the floats in sections and either assemble
them before we moved, and trailer them to Then the daggerboard
came back,
so I set to work fiberglassing it. Phil did a great job, but DHL
did their best to destroy it while
delivering it. I guess I had become complacent with the generally
good
condition that UPS boxes arrive in, and forgotten the time when boxes
were thrown off trucks and run over. DHL reminded me painfully
that it still happens. My company was acquired, which slowed things down in the workshop. I also built a couple more flat parts: the forward beam bulkheads, made from carbon, with fiberglass patches on the parts that will be cut out. I finished the daggerboard to a rough state, but it's already far better than the original. Plus, it actually fits into the trunk. I was a bit nervous because I had to grind down some rough edges for it to fit, but it slides in and out easily. As of April, I had completed 4 sections of float hull, 2 inside and 2 outside. Each section is about 8 feet long and weighs around 10 pounds. The Kevlar is a mess to work with on concave surfaces. Fortunately the vacuum bagging process resulted in only a few small voids at the turn of the gunwale, which I'll fix when I join all the parts together and add the additional laminations. I also had some problems thermoforming the Core-Cell but got better at it as I got more practice. It shouldn't be a problem to sand off as much as 1/8" on the outside of the floats since they are such a compact tubular shape to begin with. At the end of April, I decided to wait until after we've moved to continue building float parts, since they're going to be bulky to move. Plus I'm working so much that I have little time for building. Most of the time I only get into the shop once a week. I have started "tuning up" the Goody-E, repainting and reinforcing weak points. During spring and early summer I was too wrapped up in our
move to In summer 2004, I purchased nearly complete hulls and a
trailer from Matthew
Church, who was building an F9AX north of In September, Ian Farrier
announced availability of plans for the F-32 trimaran,
the home-builder's version of the F-33. I upgraded my
plans but will probably end up with a boat that's mostly F9AX. In early October, the contractor finally started building the new garage. I built rolling frames for the hull so I could lift it off the trailer and roll it around the garage. By the end of October the garage was complete. I still
had to wait for the building inspection before I could open the back of
the garage (I used the back wall as a shed roof for the winter)
because the boat barely fit diagonally and took up the entire
garage. I laid the boat
down on its side, to make glassing easier. I did my first tests
of
the Derakane Vinylester
resin on October 30th.
When the F-32 plans arrived, I was surprised to find that the
form frame spacing is identical to the F-9,
and the bow and stern foam is extended to make the boat 32 feet.
The forms are almost identical in shape, but the gunwale is about 2"-4"
higher, to accomodate the higher CMM
position, which allows for shorter beams. I decide it's not
worthwhile to try to use the F-32 beams and CMMs.
Instead I'll just use my CMMs, and get
beams from Corsair or I sanded the entire deck of the boat. Matthew faired all
of the glass on the deck (about 90%) and prepped the rest of the foam
for glassing. He didn't put some of the unidirectional in the
right position on the port forward deck so I redid it.
Because he didn't correctly glass the inside of the daggerboard trunk, and because my daggerboard is probably too fat to fit in his
trunk anyway, I to cut the trunk out of the boat and put my trunk
inside the cabin. I started fairing my daggerboard,
but I think I will look into purchasing some ready-mixed epoxy fairing
compound because it gets tedious quickly to mix resin and then mix in
fillers, plus it's hard to get consistency batch to batch. One
advantage to
building the boat in a large space and in the order specified in the
plans is that it allows
you to work on many projects at once, so when sanding becomes boring
you can always switch to something else. November 6-7, I built a deck behind the garage, hoisted the
16x8
wall on hinges, and built walls around the sides. Unfortunately,
I was so busy at work that I was travelling
for several weeks and wasn't able to do any work on the boat, except
for occasional sanding here and there. I was also concerned that
the Derakane I got from Matthew had
outlived its useful life, so I ordered 3 fresh gallons from Aircraft
Spruce. November 28th. I returned from Over the next few weeks, I completed the
hull
exterior. It required 10 pieces of glass on the hull and some
patches on deck, as well as several long sections of
unidirectional. I used 3 gallons of resin total. On
December
6th, I put the last piece of fiberglass on the outside of the
hull. In the meantime, I cut out the daggerboard
trunk. I started to fair the new glass to see how the PolyFair works, and I like it. In the cold
garage it stays workable long enough for me to do a pint at a time. Finishing the glassing on the hull was one
of the easiest jobs in the
entire boat. The Derakane was nice to work with, except for the
styrene, but I wore an organic respirator. It was a lot easier to
handle large sheets of wet glass than I thought it would be, and I
applied a lot of glass dry and wet it out on the boat. As I've
mentioned before, for the thin laminates that Farrier specifies, there
isn't much advantage to vacuum bagging, and probably not to wet layup,
where you try to squeeze out excess resin on the laminating table
before applying the cloth. Around Christmas I have some time to level the boat in preparation for installing the CMMs. |